#831- South 200th St Shared Use Path


Project Details
Client:
City of SeaTac
Project Manager:
Ed Armijo
Location:
S 200th St, Des Moines, WA
Start Date:
Oct 12, 2020
Complete Date:
May 30, 2021
Value:
$2,129,409
Share:

Project Info

Project #831, South 200th Shared Use Path is for the City of SeaTac, WA.

Scope of work includes construction of a new shared use path, utility relocation and installation of stormwater facilities, path illumination, retaining walls, driveway improvements, bioretention, ADA curb ramps and HMA pavement rehab. This project takes place between 12th Place and Des Moines Creek Park.

Follow Ceccanti on Facebook and YouTube

Location