#684 - Canyon Substation

Project Details

Owner: City of Tacoma - Tacoma Power
Contact: Kirk Kessler
Contract Value: 2,547,533.00
Date Completed: 7/30/10
Location: Tacoma, WA
Major Subcontractors:
Corona Steel, Inc.
Fine Painting & Allied Service
Keystone Masonry, Inc.
Malcom Drilling Co., Inc.
Meyer Brothers Roofing
Owl Fencing, Inc.
Pacific Coast Steel
Paramount Electric Co., Inc.

Canyon Substation

Thumb Thumb Thumb Thumb Thumb

Description

This project includes the civil construction of a transmission-level electrical substation.  This substaion is composed of two major phases: (1) substation civil construction and (2) construction of 2,700 SF control house.

Substation Civil Construction:
Clearing and stripping, excavation, grading, various underground utilities, erosion and sediment control, fencing, lighting, conduit, and grounding.

Control House Construction: